[OM] HL Pick Slip SRS Report -> Completed Warning

After Pick Release action, pick slip report will get submitted, but it often completed warning.

How to know if actual picking taken place? Picking could be failed or success even the program completed warning. E.g. For printing issue, even it completed warning, but the stock has been picked.

From Requests list, click on the request, view Output. If there is records there, it was successfully picked. Another faster way, observe the request in the list, if the 4th and 5th parameters have value, it is successful.