Labels

[ALRT] (3) [AR] (2) [BOM] (3) [GL] (2) [GTM] (1) [INV] (18) [MRP] (1) [OM] (27) [PO] (58) [QP] (3) [SYS] (39) [WIP] (4) AGIS (1) OM (1)

Thursday, December 30, 2010

[MRP] Suggested Dock Date for Purchase Order in MRP

Suggested Dock Date for Purchase Order is derived from Promised Date.

What if user did not enter Promised Date, but he has entered Need-By date only? The Need-By date will be used as dock date. (Thanks Kelvin, from Carmel, for his indirect contribution)

No comments:

Post a Comment